Looking to apply EPMD on a rubber roof that has been previously repaired with an asphalt based coating and roof cement.

0 votes
1. Clean roof and apply Proflex Primer, and use polyester mesh fabric on seams and other damaged areas.  Primer over top of the fabric again.  2- Apply EPDM coating within a day while the primer is still tacky. Any additional advice?  Such as temperature needed for application of both primer and coating?
asked Feb 27 in General by PW

2 Answers

0 votes

sure see below

Thank you

Once the ProFlex is applied, the Liquid EPDM must be applied within 24-48 hours to ensure proper adhesion. The ProFlex needs to be a little tacky when applying the Liquid EPDM. If the ProFlex is tacky but does not pull up when you walk on it that is the ideal condition to apply the Liquid EPDM. If the ProFlex is allowed to dry the Liquid EPDM will not adhere properly. This will necessitate you waiting until the ProFlex has fully dried and then sand and recoat before re-applying the Liquid Rubber. The day which you apply the ProFlex primer needs to be above 50 degrees. Lower temperatures at night will slow the cure but will not affect the product. Do not apply ProFlex if you anticipate freezing temperatures BEFORE you are able to apply the Liquid EPDM Rubber. NOTE: The above procedure is not recommended for use in climate zones that experience temperatures below zero degrees F.

answered Feb 27 by admin